Cost and Schedule Optimization in Building Projects Using an Integrated Management System in an Emerging Urban Context
DOI:
https://doi.org/10.20868/ade.2025.5642Keywords:
Gestión de proyectos de construcción, Optimización de costes y plazos, Sistema Integral de Gestión, Contexto Urbano emergenteAbstract
This study presents the implementation and validation of an Integrated Management System (IMS) aimed at optimizing costs and deadlines in multifamily building projects in Metropolitan Lima, Peru. The research was developed under a quantitative approach and a pre-experimental design, applying GIS in five projects selected according to criteria of technical comparability, accessibility to financial information and location in an emerging urban context. Projects without GIS presented an average cost overrun of 8.82%, while those managed with GIS remained at 0.54%, even considering the cost of management. In terms of time, average delays decreased from 15.54% to 7.14%. In addition, a high level of compliance with the system was observed (over 90%), reflecting its operational viability and acceptance by the technical teams. GIS proved to be an effective tool to improve traceability, inter-area coordination and decision-making on site, without requiring high technological investments. These findings confirm the hypothesis that integrated and structured management can mitigate critical deviations in building projects, especially in emerging urban contexts.
Downloads
References
1. Abani, A. J., & Ogedengbe, F. O. (2024). Optimising project cost control practices for enhanced time efficiency and quality delivery in Nigeria’s construction industry. Educational Administration: Theory & Practice, 29(4), 4140 4149. https://doi.org/10.53555/kuey.v29i4.8687
2. Alnajjar, O., Atencio, E., & Turmo, J. (2025). Framework for Optimizing the Construction Process: The Integration of Lean Construction, Building Information Modeling (BIM), and Emerging Technologies. Applied Sciences, 15(13), 7253. https://doi.org/10.3390/app15137253
3. Azhar, S. (2011). Building Information Modeling (BIM): Trends, Benefits, Risks, and Challenges for the AEC Industry. Leadership and Management in Engineering, 11(3), 241–252. https://doi.org/10.1061/(ASCE)LM.1943-5630.0000127
4. Ballard, G., & Howell, G. (2003). Lean project management. Building Research & Information, 31(2), 119–133.
5. Baltazar, B. (2022). Optimización de la calidad, costo y tiempo con el uso de gestión de proyectos en la construcción del conjunto residencial Home Town. https://hdl.handle.net/20.500.12848/4830
6. Berrio, J. (2016). Factores que afectan el costo y plazo de proyectos de infraestructura en Latinoamérica. Revista de Ingeniería Civil, 30(2), 45–58.
7. ElSahly, O. M., Ahmed, S., & Abdelfatah, A. (2023). Systematic Review of the Time Cost Optimization Models in Construction Management. Sustainability, 15(6), 5578. https://doi.org/10.3390/su15065578
8. Enshassi, A., Mohamed, S., & Abushaban, S. (2013). Factors affecting the performance of construction projects in the Gaza Strip. Journal of Civil Engineering and Management, 19(3), 246–256.
9. Hernández-Sampieri, R., & Mendoza, C. (2018). Metodología de la investigación: Las rutas cuantitativa, cualitativa y mixta (3.a ed.). McGraw-Hill Education.
10. Jiang, F., & colaboradores. (2022). Analysis of construction cost and investment planning: Multivariate cost prediction models in the construction sector. Sustainability, 14(3), 1703. https://doi.org/10.3390/su14031703
11. Koskela, L. (1992). Application of the new production philosophy to construction (Tech. Rep. No. 72). Stanford University, Center for Integrated Facility Engineering.
12. Llanque, A. (2021). Aplicación de la tecnología BIM para optimizar los costos en el presupuesto del hotel Tacna Heroica. http://hdl.handle.net/20.500.12969/2112
13. Love, P. E., Irani, Z., & Edwards, D. J. (2013). A rework reduction model for construction projects. IEEE Transactions on Engineering Management, 50(4), 413–428. https://doi.org/10.1109/TEM.2003.820217
14. Meléndez, J. (2022). Influencia del método de gestión y optimización en los costos, tiempos y calidad de las empresas constructoras: Una revisión sistemática entre 2010–2020. https://hdl.handle.net/11537/25772
15. Nicolás, F. (2009). Gestión de costes en proyectos de edificación. McGraw-Hill.
16. Pacheco, A. (2024). The Role of BIM in Innovation and Efficiency. SAGE Open, … (2024). https://doi.org/10.1177/21582440241233401
17. Rivera, A. (2024). Consequences in cost and time in construction projects due to the low level of use of BIM methodology [Artículo]. Revista Ingeniería de Construcción RIC, 39(2), 151 … https://doi.org/10.7764/RIC.00107.21
18. Ríos, R. (2017). Metodología para la investigación y redacción. Servicios Académicos Intercontinentales S.L.
19. Romero, A., & Esenarro, D. (2024). Factors Affecting Contract Compliance and Execution of Public Works in the Executing Unit: Special Project Huallaga Central and Bajo Mayo in Peru, 2022. Buildings, 14(9), 2664. https://doi.org/10.3390/buildings14092664
20. Soto, M. (2019). Diagnóstico de la gestión de proyectos de construcción en Lima Metropolitana. Revista Ingeniería y Sociedad, 12(1), 22–37.
21. Thomas, H. R., Horman, M. J., de Souza, U. E. L., & Zavřel, J. (2003). Reducing variability to improve performance as a lean construction principle. Journal of Construction Engineering and Management, 129(2), 144–154.
22. Tinoco, B. (2020). Implementación de un modelo de gestión de compras para optimizar la ejecución de los proyectos de una empresa constructora. https://hdl.handle.net/20.500.14138/3349
23. Tinoco, M. (2020). Barreras para la implementación de tecnologías BIM en el Perú [Tesis de Maestría, Pontificia Universidad Católica del Perú].
24. Uguña, M. (2019). Evaluación de la eficacia de ERP S10 en proyectos de construcción. Revista de Tecnología en Construcción, 14(2), 55–61.
25. Vizcarra, C. (2018). Diagnóstico del sistema de contrataciones públicas del Perú. Revista de Administración Pública, 23(1), 30-44
26. Yeomans, A. V., Alpuche, M. G., & Borbón, A. C. (2025). Influencia de los patrones de uso en sistemas de enfriamiento y envolvente térmica en la habitabilidad de espacios educativos. Sobre los procesos del proyecto arquitectónico (pp. 41-70). Qartuppi.
27. Zapata, M. (2011). Elementos y referencias para la formación. Revista de Educación a Distancia, 24 (3), 103-104. Recuperado de http://dx.doi.org/10.4067/S0718-07642013000300012 TABLE V
Downloads
Published
Issue
Section
License
Copyright (c) 2025 Autor / BY-NC

This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.
Anales de Edificación does not charge authors for processing or publishing an article and provides immediate Open Access to its content. All content is available free of charge to the user or his institution. Users are permitted to read, download, copy, distribute, print, search or link to the full text of articles, or use them for any other lawful purpose, without prior permission from the publisher or author. This is in accordance with the BOAI definition of open access.
- Authors retain the copyright and grant to the journal the right to a Creative Commons attribution / Non-Commercial / Non-Derivative 4.0 International (CC BY NC ND) License that allows others to share the work with an acknowledgement of authorship and non-commercial use.
- Authors may separately establish additional agreements for the non-exclusive distribution of the version of the work published in the journal (for example, placing it in an institutional repository or publishing it in a book).
Unless otherwise indicated, all contents of the electronic edition are distributed under a Creative Commons license.