Implementation model for residential housing works in Cuba applying the Lean Construction philosophy
DOI:
https://doi.org/10.20868/ade.2025.5643Keywords:
Lean Construction, Metodología, Productividad, Mejora continua, Vivienda residencialAbstract
This study explores the application of Lean Construction as a strategy to enhance productivity in the construction industry. A case study of “52 homes in the Roble neighborhood” revealed that only 45% of working time is dedicated to productive tasks, while 35% is contributive and 19.5% non-contributive. The main causes of inefficiency include poor planning, ineffective communication, disorganized job sites, inconsistent material supply, and transportation issues impacting worker attendance. A detailed analysis of key Lean tools and their implementation methodologies is presented, identifying specific opportunities for improvement. In response, an experimental Lean implementation model is developed to guide professionals and companies in adopting these practices. The findings aim to promote broader integration of Lean Construction principles across the sector to address such inefficiencies and improve overall performance
Downloads
References
1. Al Balkhy, W., Sweis, R., & Lafhaj, Z. (2021). Barriers to adopting lean construction in the construction industry—The case of Jordan. Buildings, 11(6), 222.
2. Bartolón Pérez, J. d. J., (2020), «Filosofía lean construction y su impacto en la implementación en el desarrollo de proyectos de edificación», Trabajo Fin de Grado, Repositorio Facultad de Ingeniería UNAM, http://132.248.52.100:8080/xmlui/handle/132.248.52.100/17279.
3. Bravo, P. A. V., (2021), «Los 5 beneficios del Big Room con Last Planner System®» 18 Octubre 2021. Available: https://konstruedu.com/es/blog/los-5-beneficios-del-big-room-con-last-planner-system.
4. Cacciuttolo, C., Muñoz, E., & Sotil, A. (2025). Technological Evolution of Architecture, Engineering, Construction, and Structural Health Monitoring of Bridges in Peru: History, Challenges, and Opportunities. Applied Sciences, 15(2), 831.
5. Canessa Montejo, M. F. (2009). Los derechos humanos laborales en el derecho internacional. Derecho Pucp, 63, 349.
6. Castillo, V. G., (2001). «Productividad en obras de construcción. Diagnóstico, crítica y propuesta», Pontificia Universidad Católicadel Perú Libro. https://doi.org/10.18800/9789972424175
7. Conexión Esan, (2019), «Lean manufacturing v.s. Modelo tradicional: buscando la eficiencia» 8 agosto 2019. Available: https://www.esan.edu.pe/conexion-esan/lean-manufacturing-vs-modelo-tradicional-buscando-la-eficiencia.
8. Cusihuaman, A. S. S., Cruz D. D. R. y Salazar P. A. B., (2014), «Implementación del sistema lean construction para la mejora de productividad en la ejecución de los trabajos de estructuras en obras de edificación de viviendas» Trabajo Fin de Grado, Universidad Peruana de Ciencias Aplicadas, Lima. http://hdl.handle.net/10757/566982.
9. Dallasega, P., & Rauch, E. (2017). Sustainable construction supply chains through synchronized production planning and control in engineer-to-order enterprises. Sustainability, 9(10), 1888.
10. Erazo-Rondinel, A. A., Ccoyllar, I. M., & Huaccha, A. (2023). A Study of the Benefits of Lean Construction During the Pandemic: the Case of Peru. In Proceedings of the 31st Annual Conference of the International Group for Lean Construction (IGLC31) (pp. 1350-1359).
11. Escuela Origen International Education, (2022), «Lean Construction: cómo planificar proyectos de construcción con éxito» 22 Julio 2022. Available: https://escuelaorigen.com/lean-construction-implatacion-curso/.
12. Fernández, G. B., Ccoyllar-Escobar, I. M., Huaccha-Uriol, A. E., Vilca-Fanola, A. N., & Erazo-Rondinel, A. A. (2023). A review of the implementation of Lean Construction tools during the Covid-19 pandemic. In 2023 Congreso Internacional de Innovación y Tendencias en Ingeniería (CONIITI) (pp. 1-5). IEEE.
13. Ferrán, R. B., (2022), «2021 en la Construcción: año difícil, pero de tenacidad» Trabajadores, 1 enero 2022.
14. Gilacopa Banegas A. E. y Colque Colque, R., (2020), «"Aplicación de la filosofía Lean Construction para mejorar la productividad de las obras de edificaciones en la Ciudad de Tacna» Trabajo Fin de Grado, Universidad Privada de Tacna. http://hdl.handle.net/20.500.12969/1563.
15. Gong, Q., Wu, J., Jiang, Z., Hu, M., Chen, J., & Cao, Z. (2024). An integrated design method for remanufacturing scheme considering carbon emission and customer demands. Journal of Cleaner Production, 476, 143681.
16. Hei, S., Zhang, H., Luo, S., Zhang, R., Zhou, C., Cong, M., & Ye, H. (2024). Implementing BIM and lean construction methods for the improved performance of a construction project at the disassembly and reuse stage: A case study in Dezhou, China. Sustainability, 16(2), 656.
17. Igwe, C., Hammad, A., & Nasiri, F. (2022). Influence of lean construction wastes on the transformation-flow-value process of construction. International Journal of Construction Management, 22(13), 2598-2604.
18. Lean Construction Institute, (2023), «What is Lean Construction?,». Available: https://leanconstruction.org/lean-topics/lean-construction/.
19. López Agudelo, D. O., & Caicedo Barreto, L. V. (2020). Análisis sistémico de la compañía Asercom Ingeniería SAS para la toma de decisiones (Master's thesis, Universidad Santo Tomás).
20. Li, C. Z., Tam, V. W., Hu, M., & Zhou, Y. (2024). Lean construction management: A catalyst for evaluating and enhancing prefabricated building project performance in China. Journal of Building Engineering, 94, 109930.
21. Ma, K., Yu, Y., Yang, B., & Yang, J. (2019). Demand-side energy management considering price oscillations for residential building heating and ventilation systems. IEEE Transactions on Industrial Informatics, 15(8), 4742-4752.
22. Mejía Aguilar, G. y Hernández, T. C., (2007), «Seguimiento de la Productividad en Obra: Técnicas de Medición de Rendimientos de Mano de Obra», UIS Ingeniería, vol. 6, num. 2, pag. 45-59. Available: https://dialnet.unirioja.es/descarga/articulo/6299721.pdf
23. Miranda Mejia, M., Torobisco Vilca, E. y Gomez Minaya, R., (2020), «Evaluación de la eficacia de la aplicación de last planner system en un proyecto de construcción en la etapa de acabados - arquitectura en Perú en el año de 2019», Investigación y Desarrollo, vol. 20, num. 1, pag. 193-213 (2020). Doi: : 10.23881/idupbo.020.1-14i.
24. Muñoz, P., (2019), «Qué es Lean Construction o Construcción sin Pérdidas» 18 diciembre 2019. Available: https://evalore.es/que-es-lean-construction.
25. Naor, M., Bernardes, E. S., & Coman, A. (2013). Theory of constraints: is it a theory and a good one?. International Journal of Production Research, 51(2), 542-554.
26. Orihuela, P. y Ulloa, K., (2011), «La Planificación de las obras y el Sistema Last Planner», Corporación Aceros Arequipa, Construcción Integral, Boletín num. 12. Available:
27. C. Piña Ramírez, R. Bonachea, A. Vidales-Barriguete http://www.motiva.com.pe/articulos/La_Planificacion_Obras_Sistema_LastPlanner.pdf.
28. Pérez Herrera, J. F., (2019), «¿Que es un Big Room?» 18 diciembre 2019. Available: https://www.leanconstructionmexico.com.mx/post/queesunbigroom#:~:text=The%20Big%20Room%20es%20un,el%20Last%20Planner%20System%C2%AE.
29. Pheng, L. S., & Chuan, Q. T. (2006). Environmental factors and work performance of project managers in the construction industry. International journal of project management, 24(1), 24-37.
30. Pons, J. F. y Rubio, I., (2019), «Lean Construction y la Planificación Colaborativa. Metodología de Last Planner System», Consejo General de la Arquitectura Técnica de España. ISBN: 978-84-09-10609-7.
31. Porras Díaz, H., Sánchez Rivera, O. G. y Galvis Guerra, J. A. (2014), «Filosofía Lean Construction para la gestión de proyectos de construcción: una revisión actual», Avances Investigación en Ingeniería, vol.11 num. 1 Doi: https://doi.org/10.18041/1794-4953/avances.1.298
32. Proud, J. F., (2007), «Master Scheduling Third Edition. A practical guide to competitive manufacturing», Libro, ed. John Wiley and Sons, Hoboken, New Jersey.
33. Ramos, A., (2016), «LinkedIn. LEAN: (Definición de Actividades)» 16 junio 2016. Available: https://es.linkedin.com/pulse/lean-definici%C3%B3n-de-actividades-a-liro-e-ramos.
34. Richert, T. y Vargas, A., (2022), «¿Qué es el Last Planner System®?,» 25 Julio 2022. Available: https://leanconstructionblog.com/What-is-the-Last-Planner-System-Que-es-el-Last-Planner-System.html.
35. Rodríguez, F., (2023), «a3 Lean Construction», 12 marzo 2023. Available: https://a3leanconstruction.com/guia-implementacion-last-planner-system/.
36. Rubio Pérez, I. y Pons Achell, J. F., (2021), «Lean Construction las 10 claves del éxito su implantación», Consejo General de la Arquitectura Técnica de España. ISBN: 978-84-09-27426-0.
Downloads
Published
Issue
Section
License
Copyright (c) 2025 Autor / BY-NC

This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.
Anales de Edificación does not charge authors for processing or publishing an article and provides immediate Open Access to its content. All content is available free of charge to the user or his institution. Users are permitted to read, download, copy, distribute, print, search or link to the full text of articles, or use them for any other lawful purpose, without prior permission from the publisher or author. This is in accordance with the BOAI definition of open access.
- Authors retain the copyright and grant to the journal the right to a Creative Commons attribution / Non-Commercial / Non-Derivative 4.0 International (CC BY NC ND) License that allows others to share the work with an acknowledgement of authorship and non-commercial use.
- Authors may separately establish additional agreements for the non-exclusive distribution of the version of the work published in the journal (for example, placing it in an institutional repository or publishing it in a book).
Unless otherwise indicated, all contents of the electronic edition are distributed under a Creative Commons license.